PROJECT

The Tech Group – West Pharma

LOCATION
Damastown Industrial Park Mullhuddart Dublin 15 Co. Dublin

PROJECT SUMMARY
Site Development, Substructures and Concrete Floors for 5,500m2 medical device plant.

CLIENT
Ardmac

Main Contractor:

Services:

Drainage, Tanks & Utilities

Roads & Car Parks

Substructures

Concrete Floors and Frames

Design Team:

Architect: DMOD

Engineer – M&E: 

Metec Consulting Engineers

Engineer: McElroy Associates

PQS: 

Key Features:

14,590m³ reduce level excavation.

890m³ excavation for foundations for building.

 6,670m³ of 6F2 hardcore placed as fill below floors, roads and car park.

890m³ of reinforced concrete to pad foundations.

Concrete works for 4,100m² of groundfloor.

650m² of ground floor was to an FM2 Finish.

1,446m² of upper floors.

1300m of surface & foul water drainage from 100mm – 600mm.

3.0 Km of MV and LV ducting.

820m³ attenuation tank.